- The EAS team performed a pre-construction noxious weed survey for an electric power transmission line rebuild project between Grand Coulee and Creston, Washington, as part of a federal Environmental Assessment.
- The proposed project would replace all wood-pole structures, improve existing access roads, and develop temporary access roads.
- Field surveys were conducted to identify invasive plants and noxious weeds, photograph and map their locations, and determine population density.